12 October 2003 Status at The Aquatic Hillcrest
Headline: Only Flight Tests Incomplete!
The system ran overnight and when we arrived we waited for the Sunstrobe data
collection to complete. The analysis was then performed, and the system
was adjusted a small amount. The Sunstrobe data must be taken again
overnight to verify the adjustment, and then 4A will be complete.
1D-P1 is now complete. 15E is also done. SO all the formal tests
are complete except the 10A and 10B tests, which must be witnessed flight tests.
Link to Record Run Status
Punchlists:
Remaining Items to Perform at
Radome:
- Word 1 of the Platform Control Word is indicating an intermittent fault in
the 1st LO. The word is 040210 Octal and we are also seeing a red LO
fault light on the A10 PE.
- Cable label application (after completion of 6B)
- Replace GFCI (when it arrives from Syracuse) - Bill
Need to obtain locally in Germany:
- Silicone spray lubricant
Needed from Syracuse:
Item(s) |
Requested |
DHL Air Waybill |
Picked Up |
Elapsed Days |
Status |
RF Switch |
18 September |
??? |
??? |
??? |
??? |
2nd LO Generator (11A19A6) |
24 September |
EGL |
given to EGL in Frankfurt 24 September |
9+ |
Received Syr 3 Oct |
3 Row Receivers |
30 September |
|
given to EGL in Frankfurt 30 September |
9 |
Received Syr 8 Oct |
1 Noise Detector |
30 September |
|
given to EGL in Frankfurt 30 September |
9 |
Received Syr 8 Oct |
50A Circuit Breaker |
27 September |
|
|
6+ |
Terry Moselle ordering 10/2 |
GFCI |
15 September |
|
|
|
Terry Moselle ordering 10/2 |
Maxtor ProDrive disk drive for the RES |
29 September |
|
|
4+ |
Terry Moselle ordering 10/2 |
Software to port binary files Vax - Laptop |
04 October |
|
|
|
Todd Mobley shipping 08 Oct |
Oil Sensor Part number 114840961 |
07 October |
|
|
|
??? |
Oil Sensor Part number 614810091 |
07.October |
|
|
|
??? |
GE Circuit Breaker TED134125 480VAC 125A breaker for the CB3 Transformer
in the 14A6 panel |
10 October |
|
|
|
Tim Coon procuring and expediting |
Photos from today:
|