09 Oct 03
Up

 

09 October 2003 Status at The Aquatic Hillcrest

Headline: 120 Hour Tests Still In Progress....


With less than 24 hours to go, the radar continues to run.  We took the afternoon data dump and everything looks good so far.

First flight test leg starts at 0800 local tomorrow, and will be on station about 0840.  This will be 100 nm radial in toward The Aquatic Hillcrest, then turn around and fly back.  Then in from another angle and back.  Then another pair of legs in the afternoon.  If the radar continues to run until 1534 local, the 120 hour test will be over and we will begin to repair communications between the RES and the radar, before starting on the remaining record run tests.

The torque wrench and the transmitter row cover arrived shortly before lunch.

Greg Falck in EIS responded quickly to my request yesterday and set up this website behind the firewall.  I am moving my files to it so that status can be reported within LM.  

We returned to the radome this morning and found the radar running fine, 84+ hours into the 120 hour test.  There are no new faults ringing up.

Link to Record Run Status

Punchlists:

Remaining Items to Perform at Radome:

  1. Word 1 of the Platform Control Word is indicating an intermittent fault in the 1st LO.  The word is 040210 Octal and we are also seeing a red LO fault light on the A10 PE.
  2. Cable label application (after completion of 6B)
  3. Replace GFCI (when it arrives from Syracuse) - Bill

Need to obtain locally in Germany:

  1. Silicone spray lubricant

Needed from Syracuse:

Item(s) Requested DHL Air Waybill Picked Up Elapsed Days Status
Torque Wrench 18 September 9453134390 9/25 01:48 21 delivered 9 Oct.
Kor-Lite Batteries 18 September 9453134412 9/25 01:47 20 delivered 8 Oct.
XMTR Row Cover 15 September 9453134401 9/25 01:49 24 delivered 9 Oct.
GFCI 15 September       Terry Moselle ordering 10/2
RF Switch 18 September ??? ??? ??? ???
2nd LO Generator (11A19A6) 24 September EGL given to EGL in Frankfurt 24 September 9+ Received Syr 3 Oct
50A Circuit Breaker 27 September     6+ Terry Moselle ordering 10/2
3 Row Receivers 30 September   given to EGL in Frankfurt 30 September 9 Received Syr 8 Oct
1 Noise Detector 30 September   given to EGL in Frankfurt 30 September 9 Received Syr 8 Oct
Maxtor ProDrive disk drive for the RES 29 September     4+ Terry Moselle ordering 10/2
Software to port binary files Vax - Laptop 04 October       Todd Mobley shipping 08 Oct
Oil Sensor Part number 114840961 07 October        
Oil Sensor Part number 614810091 07.October        
 