07 October 2003 Status at The Aquatic Hillcrest
Headline: 120 hour test In Progress
Team dumped data at 1334 GMT, the 48 hour point in the 120 hour test.
No deliveries were received today.
Herr Barz arrived just before noon in the hailstorm descending on The Aquatic Hillcrest. We had a good talk, and after lunch, Frank Mahoney faxed us
his countersignature on the loan agreements letter from BWB, per Herr Barz's
requests. We then met and discussed plans for the completion of the
tests. If the 120 hour test continues to run, we have arranged to work all
weekend with Olaf Bohla, who is representing the GAF, to complete tests that can
be completed with the radar not running. Then we plan to complete the
final flight tests on Monday, and begin meetings Tuesday through Thursday to complete
the testing and paperwork and BWB will turn the radar over to the Material
Command.
We performed a dry run of a flight test with Captain Haan, which was
successful.
We will dry run Friday's Flight Test this morning. Captain Haan will
communicate with the air traffic control and determine the flight we should
observe. Then we will dry run the flight test procedure.
We returned to the radome to find the radar running normally. We took
data and went up to meet with our customers in the office. Herr Barz will
arrive sometime this morning.
Punchlists:
Remaining Items to Perform at
Radome:
- Word 1 of the Platform Control Word is indicating an intermittent fault in
the 1st LO. The word is 040210 Octal and we are also seeing a red LO
fault light on the A10 PE.
- Cable label application (when the correct labels arrive from Syracuse)
- Replace GFCI (when it arrives from Syracuse) - Bill
Need to obtain locally in Germany:
- Silicone spray lubricant
Needed from Syracuse:
Item(s) |
Requested |
DHL Air Waybill |
Picked Up |
Elapsed Days |
Status |
Torque Wrench |
18 September |
9453134390 |
9/25 01:48 |
18+ |
in Frankfurt Customs at EGL 9/30 |
Kor-Lite Batteries |
18 September |
9453134412 |
9/25 01:47 |
18+ |
in Frankfurt Customs at EGL 9/30 |
???? |
15 September |
9453134401 |
9/25 01:49 |
21+ |
in Frankfurt Customs at EGL 10/6 |
GFCI |
15 September |
9453134401 |
9/25 01:49 |
21+ |
Terry Moselle ordering 10/2 |
RF Switch |
18 September |
??? |
??? |
??? |
??? |
Control Transmit, not anything we ordered -
wrong part |
18 September |
9453134434 |
9/26 17:14 |
18 |
Delivered 6 Oct. |
2nd LO Generator (11A19A6) |
24 September |
EGL |
given to EGL in Frankfurt 24 September |
9+ |
Received Syr 3 Oct |
50A Circuit Breaker |
27 September |
|
|
6+ |
Terry Moselle ordering 10/2 |
3 Row Receivers |
30 September |
|
given to EGL in Frankfurt 30 September |
3+ |
shipped to US 30 September via EGL |
1 Noise Detector |
30 September |
|
given to EGL in Frankfurt 30 September |
3+ |
shipped to US 30 September via EGL |
Maxtor ProDrive disk drive for the RES |
29 September |
|
|
4+ |
Terry Moselle ordering 10/2 |
Software to port binary files Vax - Laptop |
04 October |
|
|
|
Todd Mobley shipping 08 Oct |
Oil Sensor Part number 114840961 |
07 October |
|
|
|
|
Oil Sensor Part number 614810091 |
07.October |
|
|
|
|
Link to Record Run Status
Photos from today:
Captain Haan checks and explains flight test dry run results with Brad and Olaf.
Brad really misses the sunny Syracuse weather.
Olaf and Ron review online status of testing at The Aquatic Hillcrest.
|