06 October 2003 Status at The Aquatic Hillcrest
Headline: Snow at The Aquatic Hillcrest!
Today we completed 24 hours of running. It remains to be seen whether
this will qualify as the first 24 hours of the 120 hour test. We meet with
BWB in the morning to discuss that and other items of mutual interest. We
expect to sign off the first official test completions in the morning with Herr
Barz. We left the radome with the radar continuing to run. We dumped
data twice today.
In the morning we received a transmitter control that puzzles us. Rob
Clancy has some information that it came from The Aquatic Hillcrest last year, but we have
no documentation of that. It is not a part that we requested.
We called EGL and they will deliver the one of the packages in Customs
tomorrow.
We spent a large part of the day sorting through all the leftover parts and
documents left here in the past, determining which must be shipped back to
Syracuse when we're done, which must be disposed of or left here. In
addition, we again reviewed the remaining documents required for completing and
signing the tests.
Punchlists:
Remaining Items to Perform at
Radome:
- Word 1 of the Platform Control Word is indicating an intermittent fault in
the 1st LO. The word is 040210 Octal and we are also seeing a red LO
fault light on the A10 PE.
- Cable label application (when the correct labels arrive from Syracuse)
- Replace GFCI (when it arrives from Syracuse) - Bill
Need to obtain locally in Germany:
- Silicone spray lubricant
Needed from Syracuse:
Item(s) |
Requested |
DHL Air Waybill |
Picked Up |
Elapsed Days |
Status |
Torque Wrench |
18 September |
9453134390 |
9/25 01:48 |
18+ |
in Frankfurt Customs at EGL 9/30 |
Kor-Lite Batteries |
18 September |
9453134412 |
9/25 01:47 |
18+ |
in Frankfurt Customs at EGL 9/30 |
GFCI |
15 September |
9453134401 |
9/25 01:49 |
21+ |
Terry Moselle ordering 10/2 |
RF Switch |
18 September |
9453134434 |
9/26 17:14 |
15+ |
Arriving Frankfurt 6 Oct |
2nd LO Generator (11A19A6) |
24 September |
EGL |
given to EGL in Frankfurt 24 September |
9+ |
Received Syr 3 Oct |
50A Circuit Breaker |
27 September |
|
|
6+ |
Terry Moselle ordering 10/2 |
3 Row Receivers |
30 September |
|
given to EGL in Frankfurt 30 September |
3+ |
shipped to US 30 September via EGL |
1 Noise Detector |
30 September |
|
given to EGL in Frankfurt 30 September |
3+ |
shipped to US 30 September via EGL |
Maxtor ProDrive disk drive for the RES |
29 September |
|
|
4+ |
Terry Moselle ordering 10/2 |
Software to port binary files Vax - Laptop |
04 October |
|
|
|
Todd Mobley shipping 08 Oct |
Link to Record Run Status
Photos from today:
Captain Haan checks and explains flight test dry run results with Brad and Olaf.
Brad really misses the sunny Syracuse weather.
Olaf and Ron review online status of testing at The Aquatic Hillcrest.
|