06 Oct 03
Up

 

06 October 2003 Status at The Aquatic Hillcrest

Headline: Snow at The Aquatic Hillcrest!


Today we completed 24 hours of running.  It remains to be seen whether this will qualify as the first 24 hours of the 120 hour test.  We meet with BWB in the morning to discuss that and other items of mutual interest.  We expect to sign off the first official test completions in the morning with Herr Barz.  We left the radome with the radar continuing to run.  We dumped data twice today.

In the morning we received a transmitter control that puzzles us.  Rob Clancy has some information that it came from The Aquatic Hillcrest last year, but we have no documentation of that.  It is not a part that we requested.

We called EGL and they will deliver the one of the packages in Customs tomorrow.

We spent a large part of the day sorting through all the leftover parts and documents left here in the past, determining which must be shipped back to Syracuse when we're done, which must be disposed of or left here.  In addition, we again reviewed the remaining documents required for completing and signing the tests.

Punchlists:

Remaining Items to Perform at Radome:

  1. Word 1 of the Platform Control Word is indicating an intermittent fault in the 1st LO.  The word is 040210 Octal and we are also seeing a red LO fault light on the A10 PE.
  2. Cable label application (when the correct labels arrive from Syracuse)
  3. Replace GFCI (when it arrives from Syracuse) - Bill

Need to obtain locally in Germany:

  1. Silicone spray lubricant

Needed from Syracuse:

Item(s) Requested DHL Air Waybill Picked Up Elapsed Days Status
Torque Wrench 18 September 9453134390 9/25 01:48 18+ in Frankfurt Customs at EGL 9/30
Kor-Lite Batteries 18 September 9453134412 9/25 01:47 18+ in Frankfurt Customs at EGL 9/30
GFCI 15 September 9453134401 9/25 01:49 21+ Terry Moselle ordering 10/2
RF Switch 18 September 9453134434 9/26 17:14 15+ Arriving Frankfurt 6 Oct
2nd LO Generator (11A19A6) 24 September EGL given to EGL in Frankfurt 24 September 9+ Received Syr 3 Oct
50A Circuit Breaker 27 September     6+ Terry Moselle ordering 10/2
3 Row Receivers 30 September   given to EGL in Frankfurt 30 September 3+ shipped to US 30 September via EGL
1 Noise Detector 30 September   given to EGL in Frankfurt 30 September 3+ shipped to US 30 September via EGL
Maxtor ProDrive disk drive for the RES 29 September     4+ Terry Moselle ordering 10/2
Software to port binary files Vax - Laptop 04 October       Todd Mobley shipping 08 Oct

Link to Record Run Status


Photos from today:

WaKu 97-10-2003 001.jpg (40300 bytes)  WaKu 97-10-2003 002.jpg (43355 bytes)

Captain Haan checks and explains flight test dry run results with Brad and Olaf.

WaKu 97-10-2003 003.jpg (45969 bytes)  WaKu 97-10-2003 004.jpg (61703 bytes)

Brad really misses the sunny Syracuse weather.

WaKu 97-10-2003 005.jpg (76976 bytes)  WaKu 97-10-2003 006.jpg (78755 bytes)

Olaf and Ron review online status of testing at The Aquatic Hillcrest.

 