System running when team arrived at radome this morning. As soon as the
Loader was activated, the system experiences a beam mismatch fault and pauses.
The team is looking into the Vax to troubleshoot this repeatable error. A
possible memory overload may be the cause, but that is not yet known. A
number of Vax experts names were provided by Todd Mobley to contact if help is
needed. Farnham returns to site today/tomorrow with tools and printer
ribbons.
Item(s) |
Requested |
DHL Air Waybill |
Picked Up |
Elapsed Days |
Status |
Torque Wrench |
18 September |
9453134390 |
9/25 01:48 |
15+ |
in Frankfurt Customs at EGL 9/30 |
Kor-Lite Batteries |
18 September |
9453134412 |
9/25 01:47 |
15+ |
in Frankfurt Customs at EGL 9/30 |
GFCI |
15 September |
9453134401 |
9/25 01:49 |
18+ |
Terry Moselle ordering 10/2 |
RF Switch |
18 September |
9453134434 |
9/26 17:14 |
15+ |
Shipment on hold in Brussels, wrong delivery |
2nd LO Generator (11A19A6) |
24 September |
EGL |
given to EGL in Frankfurt 24 September |
9+ |
Received in NYC 29 Sep, to be sent to Guy Blasi |
50A Circuit Breaker |
27 September |
|
|
6+ |
Terry Moselle ordering 10/2 |
3 Row Receivers |
30 September |
|
given to EGL in Frankfurt 30 September |
3+ |
shipped to US 30 September via EGL |
1 Noise Detector |
30 September |
|
given to EGL in Frankfurt 30 September |
3+ |
shipped to US 30 September via EGL |
Maxtor ProDrive disk drive for the RES |
29 September |
|
|
4+ |
Terry Moselle ordering 10/2 |
37 pin protocol analyzer interface pod cable |
03 October |
|
|
0+ |
Greg to hand carry 4 Oct |
Logic Analyzer |
03 October |
|
|
0+ |
Greg to hand carry 4 Oct |
Software to port binary files Vax - Laptop |
04 October |
|
|
|
Todd Mobley shipping 08 Oct |