03 Oct 03
Up

 

03 October 2003 Status at The Aquatic Hillcrest

Headline: Another Pause in the Action

The system went to tactical pause after 21 hours of the 24 hour test run that precedes the 120 hour test by agreement.  The team has rearranged some parts in the Vax where it is believed the problem resides.  Some additional 11A4 boards were requested form the GAF depot.

Farnham obtained a logic analyzer and the necessary paperwork with the help of Brian Budwey and Frank Mahoney.   Todd Mobley has obtained the necessary software and licenses to allow transfer of binary files from the Vax to the laptop for e-mail transmission back to the Systems Engineering expertise in Syracuse.  This software will be shipped to the radome "overnight."

The Friday holiday in Germany did not affect support by the GAF at the Radome, which continues uninterrupted.  BWB offices were closed, which prevented any further discussion on the exchange of agreements.  All signatures discussed so far with respect to this agreement have been provided, and all parties have done their part.


Punchlists:

Remaining Items to Perform at Radome:

  1. Re-attach Row N21-N26 cable and interlock cable - Bill
  2. Word 1 of the Platform Control Word is indicating an intermittent fault in the 1st LO.  The word is 040210 Octal and we are also seeing a red LO fault light on the A10 PE.
  3. Cable label application (when the correct labels arrive from Syracuse)
  4. Replace GFCI (when it arrives from Syracuse) - Bill
  5. Replace CB9 50A breaker when it arrives from GAF or Syracuse - Bill

Need to obtain locally in Germany:

  1. Silicone spray lubricant

Needed from Syracuse:

Item(s) Requested DHL Air Waybill Picked Up Elapsed Days Status
Torque Wrench 18 September 9453134390 9/25 01:48   in Frankfurt Customs at EGL 9/30
Kor-Lite Batteries 18 September 9453134412 9/25 01:47   in Frankfurt Customs at EGL 9/30
GFCI 15 September 9453134401 9/25 01:49   Terry Moselle ordering 10/2
RF Switch 18 September 9453134434 9/26 17:14   Shipment on hold in Brussels, wrong delivery
2nd LO Generator (11A19A6) 24 September EGL given to EGL in Frankfurt 24 September   Received in NYC 29 Sep, to be sent to Guy Blasi
50A Circuit Breaker 27 September       Terry Moselle ordering 10/2
3 Row Receivers 30 September   given to EGL in Frankfurt 30 September   shipped to US 30 September via EGL
1 Noise Detector 30 September   given to EGL in Frankfurt 30 September   shipped to US 30 September via EGL
Maxtor ProDrive disk drive for the RES 29 September       Terry Moselle ordering 10/2
37 pin protocol analyzer interface pod cable 03 October       Greg to hand carry 4 Oct
Logic Analyzer 03 October       Greg to hand carry 4 Oct
Software to port binary files Vax - Laptop 04 October       Todd Mobley shipping 08 Oct

Link to Record Run Status