01 October 2003 Status at The Aquatic Hillcrest Headline: Testing Begins!!! From Brad Shannon at the site: Today we started the 120 Hour availability test. We had to start it three times and the system crashed for three different faults. We restarted the test at 8:00 pm and hopefully the test will concluded Monday evening at 8:00pm. Good news is that we have completed tests 15CP2 and 4A. Also LM Contracts in Syracuse received the letter from BWB concerning the loan of GAF material. This needs to be translated ASAP, reviewed, signed, and faxed back to BWB. A copy of the letter was received at the radome and translated verbally. It sounds consistent with all our discussions here. Farnham returned to Syracuse, Turiello did not walk. Photos from today: |