29 Sep 03
Up

 

29 September 2003 Status at The Aquatic Hillcrest

Headline: TRR Complete, Radar Working.

The meeting was held in the morning.  I began with remarks noting the wonder support and cooperation provided over the last two weeks by the GAF.  Captain Haan and I agreed that Sgt. Major Steffen Pohl should receive most of the honor for this situation.  His support was terrific and we are glad he is part of the team.

Test Director Weyer and Captain Haan, who are here at The Aquatic Hillcrest,  discussed via telephone with Herr Barz, who is in Koblenz, the recommendation to proceed with the 120 hour test immediately.  We expected to receive approval soon and begin after lunch.  While the discussions were held, Ron and Bill changed the 2nd LO Generator, to replace the engineering board that Brad brought last week with one provided by the GAF on Friday.  The GAF are also helping us locate printer ribbons, and have found a circuit breaker in the depot that we can borrow until ours is delivered.

Our team has changed slightly.  Sgt. Steffen Pohl returned late Saturday to his post.  He was a tremendous help to our team and we would not be ready to proceed without having had his help.  Our new member is Olaf Bohla, who provides Systems Support to the GAF.  He was key to finding and fixing the ITU communication problem noted below.

It has been arranged that official testing may begin once the Material Command approves that the 5 boards currently in the system shall stay in the radar permanently.  That was been approved, providing LM agrees to repair and return the 5 defective boards to the Material Command.  I have sent a Program Directive to LM Repair & Return providing the necessary direction.  We expect to begin official testing as soon as all agree the necessary agreements are in place.

Brad and Greg went to Fulda to pick up tools and parts.  When they arrived back at the radome, no formal testing had begun.  Testing may begin in the morning.  There may be some confusion over the paperwork required to begin testing.

18:30: The team got the ITU communicating with the modem cabinet.  There was an I/O board that came loose inside the ITU, and when the team re-inserted it, things began to work.  This will allow completion of the dry runs tomorrow for the 3 tests.   This is a VERY  BIG success for our team and culminates 5 days of debugging.

We received no deliveries today and we need to push on where our packages are.

19:45: Steve Burdick called to see how we are doing with the RES.  When I reported its comatose nature, he offered to check with EIS and see if they have any of these vintage disk drives that we are unable to find.  Thanks, Steve!  It's a Quantum ProDrive, supported now by Maxtor.

20:20 While Brad and Bill repaired the row 5 receiver problem, Ron and Greg attempted to tighten the oil level sensor below the pedestal.  It was NOT loose.  Another solution will be sought tomorrow.


Punchlists:

Remaining Items to Perform at Radome:

  1. Re-attach Row N21-N26 cable and interlock cable - Bill
  2. Tighten oil sensor below pedestal -  Greg
  3. Replace CB9 50A breaker when it arrives from GAF - Bill
  4. Determine fault of 3 row receivers and remedy - Brad/Ron/Bill
  5. Ship 3 row receivers and 1 Noise detector back for R&R - Greg
  6. Word 1 of the Platform Control Word is indicating an intermittent fault in the 1st LO.  The word is 040210 Octal and we are also seeing a red LO fault light on the A10 PE.
  7. Repair RES (impedes dry run of 23a App. B) (Brad working)
  8. Cable label application (Ron working, but the wrong labels were sent and correct labels have been requested [see below])
  9. Replace GFCI (when it arrives from Syracuse) - Bill
  10. Eliminate row fault somewhere in the raceway or the circulator or a cable (Bill working)
  11. Replace 2 bulbs in Unit 14 - Bill
  12. Complete dry run 23a 4.2.1.3.2 (Bill completed)
  13. Complete dry run 23a 4.2.1.3.5 (Bill completed)
  14. Repair two doors and handles on the array (Bill completed)
  15. Replace VAX backup battery (Ron completed, even though the battery that was shipped had the wrong cable, and Ron and Brad had to field modify these parts to correct things)
  16. Finish ITU communication (impedes dry run of 15E-P2, 1D-P1 and 23a 4.2.4.8) (Entire Team)
  17. Glue exciter cable in PE cabinet - Bill
  18. Glue cable in Frequency Synthesizer cabinet - Bill

Need to obtain locally in Germany:

  1. Maxtor ProDrive disk drive for the RES (impedes dry run of 23a App. B)
  2. 240V flood lamps
  3. Null modem cable
  4. Paintbrushes
  5. Solder
  6. Flux

Needed from Syracuse:

Item(s) Requested DHL Air Waybill Picked Up Status
Engineering Boards 12 September     in Frankfurt Customs
Torque Wrench 18 September 9453134390 9/25 01:48 Clearance delay as of September 29, 2003 10:05
Kor-Lite Batteries 18 September 9453134412 9/25 01:47 Clearance delay as of September 29, 2003 10:05
GFCI 15 September 9453134401 9/25 01:49 Transferred through Cincinnati Hub - USA
RF Switch 18 September 9453134434 9/26 17:14 Shipment on hold
LA30R-KA Genicom dot matrix printer ribbons 25 September     Paula ordered, Greg will bring back Saturday
2nd LO Generator (11A19A6) 24 September EGL given to EGL in Frankfurt 24 September Received in Syracuse 29 Sep, to be sent to Guy Blasi
50A Circuit Breaker 27 September     e-mailed request
Silicone spray lubricant 28 September     e-mailed request
3 Row Receivers 29 September     to be shipped to US 1 October
1 Noise Detector 29 September     to be shipped to US 1 October

Link to Dry Run Status


Photos from today:

 

Checking a cable on row 5.  Service lift is above us, raised to provide access.


Copyright (c) 1953-2015  Gazelle Software, Syracuse, NY  All Rights Reserved.   Page Last Changed 07/04/15 10:22