28 Sep 03
Up

 

28 September 2003 Status at The Aquatic Hillcrest

Headline: TRR Tomorrow!

We were all invited to the Demel's house for coffee and something to eat.  Norbert and Renata put out terrific coffee and cakes, then showed us around their home.  Norbert does amazing work and has built many greta features.  Then we had dinner, which Ron documented (see photos).  Dinner was the best - schweinhoxen, homemade pretzels, sauerkraut and mustard.

All test procedure documents are complete and assembled.  We are assembling punchlists (below) and reducing them as much as possible for the meetings tomorrow.

Punchlists:

Remaining Items to Perform at Radome:

  1. Eliminate row fault somewhere in the raceway or the circulator or a cable (Bill working)
  2. Cable label application (Ron working, but the wrong labels were sent and correct labels have been requested [see below])
  3. Finish ITU communication (impedes dry run of 15E-P2, 1D-P1 and 23a 4.2.4.8) (Brad working)
  4. Repair RES (impedes dry run of 23a App. B) (Brad working)
  5. Address discrepancies noted during hardware inspections dry runs
  6. Word 1 of the Platform Control Word is indicating an intermittent fault in the 1st LO.  The word is 040210 Octal and we are also seeing a red LO fault light on the A10 PE.
  7. Complete dry run 23a 4.2.1.3.2 (Bill completed)
  8. Complete dry run 23a 4.2.1.3.5 (Bill completed)
  9. Repair two doors and handles on the array (Bill completed)
  10. Replace VAX backup battery (Ron completed, even though the battery that was shipped had the wrong cable, and Ron and Brad had to field modify these parts to correct things)

Need to obtain locally in Germany:

  1. 240V flood lamps
  2. Maxtor disk drive for the RES (impedes dry run of 23a App. B)
  3. Null modem cable
  4. Paintbrushes
  5. Solder
  6. Flux

Needed from Syracuse:

Item(s) Requested DHL Air Waybill Picked Up Status
Engineering Boards 12 September     in Frankfurt Customs
Torque Wrench 18 September 9453134390 9/25 01:48 Processed for clearance at Cologne - Germany as of: September 27, 2003 02:14
Kor-Lite Batteries 18 September 9453134412 9/25 01:47 Processed for clearance at Cologne - Germany as of: September 27, 2003 02:15
GFCI 15 September 9453134401 9/25 01:49 Transferred through Cincinnati Hub - USA
RF Switch 18 September 9453134434 9/26 17:14 Shipment on hold
LA30R-KA Genicom dot matrix printer ribbons 25 September     Paula Ordered
2nd LO Generator (11A19A6) 24 September     shipped to US EGL air Waybill 02051838953
50A Circuit Breaker 27 September     e-mailed request
Silicone spray lubricant 28 September     e-mailed request

Link to Dry Run Status


Photos from today:

  Buddy at the shelter

  Olaf, Norbert and Brad work on a breaker panel

  Dinner with the Demels

  on the way up the mountain

  Coming back down the mountain (courtesy Hubert Merkel)


Copyright (c) 1953-2015  Gazelle Software, Syracuse, NY  All Rights Reserved.   Page Last Changed 07/04/15 10:22